Let's See Full Process of 5-Star Hotel Lighting Control Renovation

2026/04/03
Let's See Full Process of 5-Star Hotel Lighting Control Renovation
News Detail
How long did construction take? What were the results?

Last year we completed a lighting control renovation project for a 5-star hotel with a construction area of approximately 8,000 ㎡, including 238 guest rooms plus public areas.

latest company news about Let's See Full Process of 5-Star Hotel Lighting Control Renovation  0
Client Core Requirements
  1. Three lighting scene modes for corridors and lobby: Day Mode / Night Mode / Cleaning Mode
  2. Guest rooms supporting one-touch switching between Welcome Mode and Sleep Mode
  3. Energy consumption reduced by more than 20% compared with before renovation
latest company news about Let's See Full Process of 5-Star Hotel Lighting Control Renovation  1
Final Solution

Schneider C-Bus System + DALI Dimming Drivers

  • Public areas: 6 groups of C-Bus main control modules, covering lobby, restaurant and corridors
  • Guest rooms: Wiser wireless modules for wall-drilling-free construction
  • Backend: Hotel management system integrated with KNX for remote control of all lighting scenes from the front desk
Construction Period

45 days (including 12 days for commissioning)

latest company news about Let's See Full Process of 5-Star Hotel Lighting Control Renovation  2
Post-Renovation Data
  • Monthly average energy consumption reduced by 28%
  • Guest satisfaction score for lighting increased from 3.8 to 4.6
  • Property management labor costs reduced by approximately 40%
latest company news about Let's See Full Process of 5-Star Hotel Lighting Control Renovation  3

After project completion, the client directly referred two more hotel projects to us. This kind of reputation is the best marketing.